Week ending Date | Completion Elements | Volunteer Groups |
|---|
| 7/11/2004 | Family occupancy | |
| 7/4/2004 | Dedication | |
| 5/23/2004 | Vinyl flooring Interior doors | |
| 5/16/2004 | Basement stairs and stairwell Porch soffit and fascia trim 1/2 of garage soffit 2/3 of basement band board insulation | Appraisal Institute |
| 5/9/2004 | Drywall West siding, soffit & fascia trim | Hyatt Hotel, Thursday Crew, Watterson High School, St Charles High School |
| 5/2/2004 | 2/3 of drywall Removed basement stairs Framed 1/2 wall by stairway Rear siding | Tuesday Crew, Thursday Crew, Watterson High School, St Charles High School |
| 4/25/2004 | 1/3 of dryall 2/3 of rear siding | Capital City Consulting, Thursday Crew, Watterson High School |
| 4/18/2004 | Insulation Rear pump jacks East siding | Appraisal Institute, Watterson High School, Thursday Crew |
| 4/11/2004 | Caulking & insulation baffles 1st floor wiring rough-in East soffit & fascia trim Garage siding prep Conductor lines Remove door opening bottom plates | Retirement Management Systems, Columbus College of Art & Design, Watterson High School, Speeds Electric |
| 4/4/2004 | Front soffit East pump jacks 1/2 of rear siding | Big Bear Chuck BB Memorial Group |
| 3/28/2004 | 2/3 of east siding 1/4 of rear siding | Student athletes from Brookhaven, Beechcroft and Northland High Schools |
| 3/21/2004 | Staircases Interior framing More siding details | Tuesday Crew, Thursday Crew, Big Bear Chuck BB Memorial Group |
| 3/14/2004 | Windows Interior partition placement Sided 2/3 of west and 1/3 of east sides | WKHS HomeBase, Thursday Crew, Ohio State Moritz College of Law Community Service Project |
| 3/7/2004 | Most Dow Styrafoam insulation Porch roof framing Exterior doors | Thursday Crew, WKHS HomeBASE, OSU Newman Center |
| 2/29/2004 | House and garage roof shingles Front porch roof trusses Most 2nd floor wall assembly | Thursday Crew, WKHS HomeBASE, St. Charles High School Juniors, Union Savings Bank, St. Matthews Catholic Church of Gahanna |
| 2/22/2004 | House roof construction and tar paper Garage roof construction and tar paper Basement shelves Garage & porch floors | Thursday Crew, Peace Lutheran Church of Gahana, WKHS HomeBASE, OSU Campus HfH Chapter |
| 2/15/2004 | Second floor exterior walls Porch beam assembly | OSU ??? Fraternity, OSU Campus HfH Chapter, WKHS HomeBASE |
| 2/8/2004 | Second floor sheathing Second floor front & back walls Gable end preparation | WKHS HomeBASE, St. Thomas More Newman Center, OSU Campus HfH Chapter |
| 2/1/2004 | Second floor joist system One third of 2nd floor sheathing | Thursday Crew, Nationwide Insurance, WKHS HomeBASE |
| 1/25/2004 | Straightened & braced first floor walls Installed double-top plates Second floor wall plates | Thursday Crew, WKHS HomeBASE |
1/19/2004 MLK Day | First floor load bearing walls Garage walls | Alpha Phi Alpha Fraternity, Columbus Church of Christ, OSU MLK Day group, OSU Campus HFH Chapter, WKHS HomeBASE |
| 1/18/2004 | First floor joist system First floor sheathing Basement, garage foundation, utilities First floor wall plates | Thursday Crew, WKHS HomeBASE |