Ending Date | Pictures Link | Work Groups | Accomplishments |
|---|
| 12/20/2007 |  | Everyone! | 224 Schultz Ave Dedication Ceremony |
| 12/19/2007 |  | Everyone! | 228 Schultz Ave Dedication Ceremony |
| 12/18/2007 | None Available | House Lead | Punchout; Paint garage door |
| 12/15/2007 | None Available | Individual volunteers | Punchout; Paint front & rear doors; cleaning |
| 12/14/2007 | None Available | Habitat Affiliate Staff | Punchout; cleaning |
| 12/13/2007 | None Available | Thursday Crew | Punchout; cleaning; install carpet protector |
| 12/12/2007 | None Available | House Leads | Punchout; cleaning |
| 12/10-11/2007 | None Available | Contractor | Install carpet |
| 12/8/2007 | None Available | Individual volunteers | Paint touchup; install towel bar; install mirror; install basement stairway baseboard; install linen closet shelves; repair "plumber's window"; prep floor for carpet |
| 12/7/2007 |  | Abbott Nutrition | Final paint; wash windows; install screens; nail baseboards; install towel bars; install closet shelves; |
| 12/6/2007 | None Available | Thursday Crew | Install towel bars; final paint; install basement handrail; install bypass door guide blocks |
| 12/4/2007 | None Available | Tuesday Crew | Install baseboard; install gutter guards |
| 12/3/2007 | None Available | House Leads | Install front door vinyl; begin final paint |
| 12/1/2007 |  | Archer, Meek, Weiler Agency; individual volunteers Lunch by Faith Force Volunteers | Install porch soffit; install house numbers; install front door underlayment, baseboard; complete interior doors; poly stairway handrail; install walk stones to garage; putty trim nails; install light bulbs; paint mailbox; fill screws in door kick panels |
| 11/30/2007 | None Available | House leads | Paint porch railings; stain stairway handrail |
| 11/29/2007 |  | Thursday Crew | Install baseboards; install half-bath vanity; complete kitchen cabinets and countertops; install closet by-pass doors |
| 11/28/2007 | None Available | House leads | Kitchen cabinets & countertops; paint front porch railings |
| 11/27/2007 |  | Tuesday Crew | Install most interior doors; install most kitchen cabinets; install window trim; patch drywall; paint cold air returns |
| 11/26/2007 | None Available | House leads | Install vinyl flooring |
| 11/24/2007 | None Available | Vineyard; individual volunteers | Complete interior painting; complete vinyl floor underlayment & templates; paint basement shelves |
| 11/23/2007 | None Available | Individual volunteers | Interior painting; vinyl floor underlayment |
| 11/21/2007 | None Available | House leads | Paint porch railings |
| 11/20/2007 | None Available | Tuesday Crew | Paint porch railings; insulate 224 |
| 11/17/2007 |  | Individual volunteers; Lunch by Bethel Presbyterian Church | Complete porch railings; paint front porch railing; begin 224 porch; complete 224 siding & trim |
| 11/16/2007 |  | AIMCO; Individual volunteers | Install front handrails; install rear porch railings; install 224 and Guilford porch footers; sort materials and clean garages; silence floor squeaks |
| 11/15/2007 | None Available | Thursday Crew | Insulate 224 |
| 11/14/2007 |  | AIMCO; Individual volunteers; Lunch by The Worthington Senior Retirement Community | Install sod and shrubs; Install front porch railings & handrails; prep & paint porch railings; shingle 224 porch roof; trim rear porch beam & posts; |
| 11/13/2007 |  | Individual volunteers | Install front porch railing frames |
| 11/10/2007 |  | Marysville United Methodist Church; Columbus Academy; individual volunteers | Finish 228 siding & fascia trim; finish 224 porch railings and begin 228's; finish 224 north siding; finish 224 gable end soffit and fascia; install porch stairway railing posts |
| 11/9/2007 |  | Limited Brands; Individual volunteers | Install F-channel, soffit and siding on front gable; complete siding on both garages; install 224 porch railings; caulk floor/wall joint in 224; insulate 228 band boards |
| 11/8/2007 |  | Thursday Crew; Thursday Evening Crew | Install F-channel on front gable; install garage overhead door trim; install final back porch post; complete insulation; complete 224 back siding; trim 224 front posts; complete 224 interior framing |
| 11/7/2007 |  | Citi Fund Services | Caulk floor/wall joint; seal windows and doors; install insulation baffles; repair floor gaps; eliminate truss squeak; frame closets over stairs; install Dow insulation board on front gable |
| 11/6/2007 |  | Tuesday Crew | Back gable siding complete; garage aluminum trim complete; Construction locks installed; Window sealing begun; Aluminum beam trim 75% complete; Front porch post trim complete; 224 north siding 98% complete; 224 east siding 85% complete; 224 over stairway storage framed; |
| 11/3/2007 |  | Mifflin Presbyterian Church; individual volunteers; Able Roofing | South siding complete; garage north, west and south siding complete; garage soffits complete; garage aluminum trim 50% complete; Dow insulation board complete on upper back gable end; basement stair safety railings complete; roofing complete; 224 north siding 98% complete; 224 east siding 60% complete; 224 garage aluminum trim complete; |
| 11/2/2007 |  | Limited Brands; HFH-GC affiliate staff; Lunch by Bobbie Weiler | South siding complete; garage south side 80% sided; garage door installed; garage north soffit complete; 224 siding continued, garage aluminum trim complete |
| 11/1/2007 |  | Thursday Crews | North, rear & front porch siding complete; Attic access, over-stairs closet and misc framing details complete; garage siding prep begun; 224 siding continued, beam trim complete, garage 75% complete |
| 10/31/2007 |  | Limited Brands | North siding 95% complete; Rear siding 90% complete; Front porch siding 60% complete; 224 North and South Siding complete to below ladder level |
| 10/30/2007 |  | Tuesday Crew | Complete house soffits; begin fascia trim; prep and side back porch; siding prep on front of house; frame garage door rough opening |
| 10/29/2007 | | House lead | Frame soffit ends; siding repairs |
| 10/27/2007 |  | Archer, Meek, Weiler Agency; Women's Build; Individual volunteers; Lunch by Vineyard of Columbus | Complete Dow board insulation on garage; install soffits on porches and north side of house; begin siding north and south sides of house; install doors |
| 10/26/2007 |  | Limited Brands | Tarpaper garage roof; sheathe and tarpaper porch roof; complete garage door; begin door installation; install F-Channel and soffit; install hurricane clips; install Dow insulation board; continue framing closet over basement stairs |
| 10/25/2007 |  | Thursday Crew | Continue garage Dow board insulation; F-Channel; Re-flash windows; begin garage door; wrap porch beams |
| 10/24/2007 |  | Arlington Bank; individual volunteer | Build basement shelving components for 3 houses; install 2/3 of shelving over basement stairs |
| 10/23/2007 | | | Rained out |
| 10/22/2007 | | House lead | Begin soffits; tarpaper roof |
| 10/20/2007 |  | Individual volunteers; Lunch by Faith Force Volunteers | Frame garage door opening; continue Dow board insulation; cabinet and handicap grab bar blocking; drywall blocking; begin porch beam; wind braces |
| 10/19/2007 |  | Limited Brands; JP Morgan Chase | Complete garage roof; continue Dow board insulation; cabinet blocking; curtain blocking; install doors |
| 10/17/2007 |  | Citi Fund Services; Alcatel-Lucent; Lunch by The Worthington Senior Retirement Community | Install almost all windows on both houses; garage trusses and begin sheathing; staircases in 3 houses; garage shelving |
| 10/16/2007 |  | Limited Brands; Tuesday Crew | Continue blue board insulation; Prep garage walls & trusses; Complete roof trim boards; Repair window rough opening |
| 10/13/2007 |  | Individual volunteers; Mifflin Presbyterian Church; OSU students | Complete roof sheathing; continue blue board insulation; frame ceiling in basement stairway |
| 10/12/2007 |  | Limited Brands; Simpson Strong Tie | Begin roof sheathing; begin blue board insulation; install hurricane clips; build garage walls |
| 10/11/2007 |  | Thursday Crew | Sub-fascia; certify wall sheathing; hurricane clips |
| 10/10/2007 |  | Limited Brands; Columbus Crew | Set gable-end trusses; drywall nailers |
| 10/9/2007 |  | Principal Financial; Tuesday Crew | Prep and set trusses on house and garage; finish interior walls |
| 10/6/2007 |  | Individual Volunteers; Lunch by LPN Association of Ohio, Division 12 | Continue wall building and porch beams |
| 10/5/2007 |  | Nationwide Children's Hospital Center for Injury Research and Policy | Continue wall building and porch beams |
| 10/4/2007 |  | Thursday Crew | Continue wall building; begin porch beams |
| 10/3/2007 |  | Columbus Crew | Continue wall building |
| 10/2/2007 |  | Tuesday Crew | Complete exterior walls; begin interior walls |
| 9/29/2007 |  | Individual volunteers | Continue wall building |
| 9/28/2007 |  | Citi Fund Services; Columbus Academy; Fisher College of Business | Continue wall building; cover band boards with OSB |
| 9/27/2007 |  | AEP Financial Reporting | Continue wall building; Rain out; Wall raising ceremony |
| 9/26/2007 |  | Citi Fund Services | Begin wall building |
| 9/25/2007 |  | Citi Fund Services | Install floor sheathing |
| 9/22/2007 |  | Grace Brethren Church | Install floor joists and band boards |
| 9/21/2007 |  | House lead | Complete sill plates; Mark joist layout |
| 9/19/2007 |  | Citi Fund Services | Complete center support beam; Install 80% of sill plates |
| 9/18/2007 |  | Tuesday Crew | Begin center support beam |
| 9/17/2007 |  | Contractors | Site preparation; basement walls |